| Spec | Before | After |
|---|---|---|
| Vegetative | ||
| Fixture Model | N/A — New Construction | SpecGrade Flora-10 |
| Quantity | 0 | 24 |
| Watts (each) | 0W | 300W |
| Light Output | N/A | 664 µmol/s |
| Rated Lifetime | N/A | Q90 >40,000 hrs |
| Flower | ||
| Fixture Model | N/A — New Construction | Gavita Pro RS 2400e |
| Quantity | 0 | 123 |
| Watts (each) | 0W | 810W |
| Light Output | N/A | 2,433 µmol/s |
| Rated Lifetime | N/A | TBD |
"Left Coast filed as new construction, which usually means a longer runway with National Grid — there's no retrofit baseline to point to, so every fixture has to be justified from the design specs alone. We built the case room by room across Vegetative and Flower, tracked down equipment they'd already purchased ahead of the filing, and got $131,505 approved. For a facility this size, that's a rebate that meaningfully offsets the buildout."
Total Project Cost
$227,974
Eligible Incentives Identified
$131,505
Utility Approved Rebate
$131,505
R&D Tax Credits
$0
Final Project Cost After Rebates
$96,469
Schedule a free rebate audit — zero upfront cost, zero obligation.
Schedule a Free Rebate Audit